BIR Ruling No. 392-2022 confirms zero-rated VAT on local purchases for renewable energy developers, covering development, construction, and commercial power generation.
Renewable energy developers registered with the Department of Energy are now explicitly entitled to zero percent value-added tax (VAT) on their local purchases of goods and services used in the development, construction, and installation of power plant facilities, covering the entire process from exploration to commercial power generation.
Philippine Geothermal Production Company, Inc. (PGPC), a wholly owned subsidiary of SM Investments Corporation, operates geothermal energy projects in Tiwi, Albay, and Makiling-Banahaw, Batangas. PGPC sought confirmation that its purchases of local goods, properties, and services for the development and operation of its geothermal facilities are exempt from the standard 12% VAT under Section 15(g) of Republic Act No. 9513, the Renewable Energy Act of 2008. The projects are registered with the Department of Energy as Renewable Energy (RE) Developers and have corresponding Board of Investments (BOI) certificates supporting fiscal incentives.
The Bureau of Internal Revenue confirmed that PGPC’s local purchases of goods and services necessary for plant development, construction, installation, and the exploration and development of renewable energy sources up to conversion into power shall be subject to zero percent VAT. Section 15(g) of RA No. 9513 provides that all RE Developers are entitled to zero-rated VAT for such purchases, including services performed by subcontractors or contractors. The ruling emphasizes that this exemption applies to the entire development and commercial stage, including commercial operations, and is limited to the registered activities and projects enumerated in the ruling. The BIR also clarified that zero-rating is subject to post-audit verification to ensure proper utilization of goods and services for these projects BIR Ruling No. 392-2022 .
For RE Developers like PGPC, local suppliers of goods and services should not include the 12% VAT in their invoices for qualifying transactions related to renewable energy projects. Companies must maintain proper documentation to substantiate that the purchased goods or services are indeed used in the development, construction, and installation of power plant facilities and for exploration and development up to conversion into power. Suppliers remain responsible for accurate invoicing and remittance reporting. BIR post-audit verification ensures compliance, and any misrepresentation or use outside the covered activities may void the zero-rated VAT treatment.
BIR Ruling No. 392-2022 provides clear guidance for renewable energy developers and their suppliers, establishing a firm legal basis for zero-rated VAT on local purchases essential to geothermal and other renewable energy projects. CFOs, tax managers, and corporate counsel should ensure compliance with documentation requirements and monitor post-audit verification procedures to fully benefit from this fiscal incentive, reinforcing the governmentโs policy to promote renewable energy development in the Philippines.