BIR Ruling No. 805-2019: VAT Zero-Rating for Renewable Energy Developers

BIR Ruling No. 805-2019 confirms zero-rated VAT for DOE-certified Renewable Energy Developers on local purchases for power plant development, construction, and installation.

Renewable Energy (RE) Developers purchasing local goods and services for the development, construction, and installation of power plant facilities are entitled to zero percent value-added tax (VAT), reducing project costs and enhancing investment incentives for renewable energy projects.

EDC Burgos Wind Power Corporation, a DOE-certified RE Developer registered with the Securities and Exchange Commission and the Board of Investments, requested confirmation that its local purchases of goods, properties, and services necessary for its 150 MW Wind Energy Power Generation Project in Burgos, Ilocos Norte, qualify for VAT zero-rating. The company, organized under Philippine law, holds Certificates of Registration and Confirmation of Commerciality issued by the Department of Energy and is covered by Wind Energy Service Contract No. 2009-09-004. This request is significant because VAT zero-rating directly impacts the cost structure of renewable energy projects and aligns with fiscal policies promoting sustainable energy development BIR Ruling No. 805-2019 .

Section 15(g) of Republic Act No. 9513, the Renewable Energy Act of 2008, provides that RE Developers are entitled to zero-rated VAT on local purchases of goods, properties, and services used in the development, construction, and installation of renewable energy facilities. This incentive extends to all stages, including exploration, development, and conversion of renewable energy sources into power, including services performed by contractors and subcontractors. The ruling clarifies that suppliers of goods and services to DOE-certified RE Developers should not charge the standard 12% VAT on transactions used exclusively for plant development and installation. The BIR further emphasized that post-audit verification will ensure that purchased goods and services are applied to the specific renewable energy project, and the processing of zero-rated VAT applications must follow Revenue Memorandum Order 7-2006 and related regulations BIR Ruling No. 805-2019 .

Businesses supplying goods and services to RE Developers for registered renewable energy projects must adjust their invoices to reflect 0% VAT on qualifying transactions. While the standard VAT rate of 12% is not applied, suppliers must maintain proper documentation to support zero-rated claims, and RE Developers must ensure purchases are strictly used for project development, construction, and installation. The BIR retains the right to conduct post-audit verification, and any misrepresentation or misuse of zero-rated VAT status may result in the ruling being declared null and void. Compliance with RMO 7-2006 and RR No. 16-2005, as amended, is required for processing VAT zero-rated transactions BIR Ruling No. 805-2019 .

The ruling sets a clear precedent reinforcing the fiscal incentives available under RA No. 9513, providing certainty for RE Developers and their suppliers. It underscores the importance of accurate project documentation and adherence to BIR procedures, facilitating investment in renewable energy while ensuring transparency and proper tax administration.