BIR Ruling No. 751-2018 grants zero percent VAT to DOE-certified Renewable Energy Developers for local purchases used in hydropower plant development.
Renewable Energy developers purchasing local goods and services for the development, construction, and installation of hydropower plants are entitled to zero percent (0%) value-added tax under Section 15(g) of RA No. 9513, providing significant cost savings for approved projects.
Turbines Resource & Development Corporation (TUREDECO), a Philippine corporation duly registered with the SEC (Company Registration No. CS200431472) and the Department of Energy (DOE Registration No. HSC 2011-12-153), operates as a Renewable Energy Developer. TUREDECO manages a 9 MW Run-of-River Minihydropower Plant located in Barangay Lumbia, Cagayan River, Cagayan de Oro City, and has a confirmed commercial capacity averaging 58.19 GWh annually. The company requested certification that its local purchases of goods and services for the project would be exempt from the standard 12% VAT, relying on incentives provided under the Renewable Energy Act of 2008.
The Bureau of Internal Revenue affirmed that under Section 15(g) of RA No. 9513, all Renewable Energy Developers certified by the DOE are entitled to zero-rated VAT on local purchases necessary for the development, construction, and installation of plant facilities. This ruling applies specifically to TUREDECO’s Limbatangon Hydropower Project. Suppliers of goods and services to DOE-certified RE developers are instructed not to charge 12% VAT. The BIR further clarified that the zero-percent VAT applies only to purchases directly used for the development and installation of the plant and remains subject to post-audit verification under Revenue Memorandum Order No. 7-2006 and Revenue Regulations No. 16-2005, as amended.
For TUREDECO and similar DOE-certified RE developers, local suppliers must issue invoices without including the 12% VAT on qualifying goods and services. Businesses availing of the zero-rated VAT incentive must maintain clear documentation demonstrating that purchases are used for plant development and installation. The zero-rating benefit reduces project costs, enhances cash flow, and streamlines compliance with BIR reporting requirements, although post-audit verification ensures that only eligible expenditures receive the tax incentive.
This ruling establishes a clear precedent for Renewable Energy Developers that local purchases for approved hydropower and renewable energy projects are exempt from VAT. Companies can leverage this incentive to reduce construction and installation costs while ensuring compliance with BIR post-audit procedures, reinforcing the government’s support for renewable energy development in the Philippines.