BIR Ruling No. 780-2019 confirms that DOE-certified renewable energy developers enjoy zero-rated VAT on energy sales and local purchases for plant construction.
Renewable Energy developers manufacturing biodiesel are entitled to zero percent value-added tax on both the sale of energy generated from renewable sources and on their local purchases of goods and services used in plant development and construction.
Archemicals Corp., a Philippine corporation registered with the SEC under Registration No. CS201539357 and with the DOE as a Renewable Energy Developer of Biomass Resources (Certificate No. RE-B2017-01-124), requested confirmation that its sale of biodiesel and local purchases for plant construction qualify for 0% VAT under the Renewable Energy Act of 2008 (RA No. 9513). The companyโs plant is located in Brgy. Natumolan, Tagoloan, Misamis Oriental. The request reflects the broader effort of RE developers to ensure compliance while benefiting from incentives designed to promote renewable energy projects.
Under Section 4.108-5 of Revenue Regulations No. 16-2005, as amended, the sale of power or fuel generated from renewable sources such as biomass, solar, wind, hydropower, geothermal, ocean energy, and emerging technologies like fuel cells and hydrogen fuels is subject to zero percent VAT. Section 15(g) of RA No. 9513 further provides that Renewable Energy Developers are entitled to zero-rated VAT on local purchases of goods, properties, and services necessary for the development, construction, and installation of plant facilities. The BIR clarified that zero-rating applies strictly to the sale of energy and does not extend to maintenance or operational services of the power plants. Verification through post-audit ensures that purchased goods and services are actually utilized in plant development and construction, consistent with Revenue Memorandum Order 7-2006 in relation to RR No. 16-2005.
For businesses like Archemicals Corp., zero percent VAT applies to both the sale of biodiesel and the procurement of local supplies, provided that the goods and services are used in constructing and developing renewable energy facilities. Suppliers should not impose 12% VAT on these transactions. RE developers must maintain documentation evidencing that purchases are exclusively for plant development and construction. VAT returns must be filed as usual, but with zero-rated sales and purchases appropriately reported, and all claims remain subject to BIR post-audit verification.
The precedent set by BIR Ruling No. 780-2019 reinforces the application of RA No. 9513 incentives, clarifying that DOE-certified RE Developers enjoy a clear VAT exemption framework, subject to verification, thus encouraging investment in renewable energy infrastructure while ensuring proper tax compliance.